Feb 132018
 

We started early today about 9am as there was a forecast of rain coming at around lunch time so we thought we would get as much as we can on sorting and counting the Oak Timber. We had three more packs to go, one small one and two large ones!
So there we were, measuring and hauling one layer at a time, around to the storage rack and we carried on .. and on .. and on .. and on .. waiting for the rain to come! It went past lunch time .. and we still worked .. and worked .. and finally we actually got ALL the rest of the Oak timber all classified and quantified and moved to our now very populated storage rack!!

Oak Timber Finally All Classified and Quantified!

Oak-Rack-Full-Front

Oak Timber Finally All Classified and Quantified!

Oak-Rack-Full-Back



And guess what? We were just tidying up and bringing in various tools like ladders and things .. and the rain came! Talk about good timing! Smile!
That was one long 6 hours stint (we carried about 2 tons of wood)! Phew!

The oak delivery had 600 pieces varying from 90 to 320 mm wide and 25 to 55 mm thick, with a total weight of over 5 tons.

 Posted by at 2:55 pm
Feb 122018
 

This afternoon, while we had some nice weather, even though it was quite chilly, we went and got our odd “N” rafter (the middle one, which is number 6) up and installed. We had to plane the end a fair bit as it was a complex shaped ends and we had wondered whether we had removed enough in the workshop. So it was a case of removing more until it fitted nice and tight.
We then measured the next subset of rafters on either side, these being the triangular sections going up to the steel I-Beam and down to the outside corner. These are now in our spreadsheet!
We did also the same for the “O” section and took measurements for the similar shaped triangular sections for the 45 degree sloping roof too.
We now have finally collected this data and we now have the means to continue working in the workshop while the weather is bad outside and try not to lose too much more time due to the weather!
We hope!
Grin!

 Posted by at 5:45 pm
Feb 122018
 

Today, Monday, we resumed the task of quantifying our Oak timber and moving each plank around to our made-for-purpose storage rack. We did some sorting on Saturday but only for the morning before the rain came at lunch time. And this afternoon, instead of carrying on with this task, we decided to get our odd […]

 Posted by at 1:18 pm
Feb 102018
 

Work has been patchy over the last three days, with other commitments on Thursday, rain all day Friday and also rain in the afternoon of Saturday too! Erk! We didn’t have any other jobs lined up as we didn’t have the “N” rafter (number 6) installed so we could measure the next set of rafters […]

 Posted by at 6:00 pm
Feb 072018
 

This afternoon, in the middle of our lunch hour (about 1:30pm), the Oak Timber arrived!! There were ten packs in total, in four stacks  on the back of the lorry. Also, on the back of the lorry, was a fork-lift truck which came down two steep ramps off the end! We were lucky that the […]

 Posted by at 5:01 pm
Feb 072018
 

This morning, while we wait for the delivery of our Oak Timber, we got on with the task of cutting angled bevelled ends on the latest batch of rafters we made yesterday. These have quite a sharp angle, very deep, at 53° and almost 100mm deep. Our slicing Saw machine performed very well! And this […]

 Posted by at 12:41 pm
Feb 062018
 

This afternoon, having completed the production of the four rafters (for the “P” and “N” sections), we couldn’t go outside as it was snowinging quite hevily!! Tomorrow, we have our Oak Timber arriving, during the day sometime, and with the cold snap occurring this week all over the country, it is unlikely that we will […]

 Posted by at 6:00 pm
Feb 062018
 

Today and yesterday, we resumed our factory production line to produce the remaining rafters for completing the “P” section of the roof, as well as the first one of the “N” section. It was amusing to see us racking our brains for all the steps of the procedure of making rafters, getting all the tools, […]

 Posted by at 3:52 pm
Feb 032018
 

The last two days has fallen foul of the side-effects of the suffering these cold and flu viruses, with disrupted sleep patterns and secondly infections. What a world we live on! What will be around the next corner?? Phew!

 Posted by at 6:00 pm
Feb 012018
 

Before the rain arrived (about 3pm ) we got out there to get up and installed the six rafters we had made way back before Christmas, into the “P” section of the roof. These rafters were simple straight ones coming down from the O Ridge beam to the “P” wall, four of them had full […]

 Posted by at 4:02 pm