Category: Walls

  • All Window and Door Sub-frames are now Complete

    Back to work after two days of interruption’s , we resumed the task of putting together the Lintels and Framework around all the Windows and Doors.

    We had 7 more openings to finish off where the short vertical studs are put in above the Lintels and got those done just before lunch.

    Then we fetched another five lengths of the 89mm CLS timber off our pallet (we have virtually used up one of the two pallets bar 2 lengths!) and brought them in our workshop to be chopped into:

    • 9 x 1711 mm pieces
    • 2 x 1100 mm (using the off cuts of above)
    • And 1x 480 mm piece (also taken from the left overs of above)

    We then ripped down the middle of the timber planks, to make equal sized (about 43mm wide) pieces. One would go on the bottom sill on all the 12 windows, and the other half went up on the underside of the lintel. These pieces are designed to allow us to have space for roller blind mechanisms to be fitted below and above the window unit.

    After lunch, we went around fitting all these half pint pieces on all the windows, trimming them down so they just fitted in nice and tight, glued into place and then screwed down in several places (four points for the widest windows, three for the medium sized ones and two fixing points for the narrowest).

    Final-parts-of-Window-Subframes-1

    Final-parts-of-Window-Subframes-1

    Final-parts-of-Window-Subframes-2

    Final-parts-of-Window-Subframes-2


    We finished off the day by dismantling one of our scaffolding towers and moved the 2 castors over to our existing tower to make it much easier to move around.

    The next job is to slice up half a dozen cement boards into narrow strips of about 300mm wide and go around the whole building putting on the second layer and after that, the final third layer using whole sheets again, but making sure whole sheets bridge completely over each Window and Door for maximum strength and racking, without any joints in the middle.

  • Last Door Frame is Done and All Lintels Are In Place

    Today, under another glorious and hot sun, we finished off the final Door vertical framework (the Utility Room Back Door), which came out as 1041 mm to 1042 mm wide, in various places from top to bottom, this door will be a single extra wide style to allow better access for bigger items to get into our house.

    We then carried on with the next job of putting the Lintels over all the Windows and Doors. We measured and cut to size each opening, the two layers of 89mm CLS timber, glued and nailed together and also nailed down onto the vertical legs. There were 15 openings all to together, and we made sure that all of them were within 1mm to 2mm of being horizontal, putting in solid wooden spacers where necessary to make adjustments.

    Door-sub-Frame-completed-with-Lintels

    Door-sub-Frame-completed-with-Lintels

    Window-sub-Frame-completed-with-Lintels

    Window-sub-Frame-completed-with-Lintels


    Tomorrow, we will first measure the long diagonal rafters that forms the valleys, hips and ridges of our roof, so we can double check against our drawings to know exactly what we need to order from the specialised timber manufacturer, the man-made laminated veneer lumber called LVL. This material is basically lots of thin layers of wood, just like plywood but 200mm thick and can come up to 12metres long – wow! After that piece of survey work, we then carry on with putting in all the vertical short studs that connects the lintels to the Top-Plate, and once this is done, with one or two other little jobs, we then can continue putting up the second line of cement boards!!

  • Windows and Doors Framing Progresses

    On this lovely warm Monday, we carried on adjusting, gluing and fixing into place the remaining six window subframes going around the Great Room, the Kitchen and lastly the Entertainment Room. We had our framing template which is exactly 1708 mm wide so that all our 6 foot width windows will be the same. We then did the two 4 foot windows (the side of the Great Room and the Utility Room) making them both 1098 mm wide and finally, we did our only 2 foot window in the side of the Front Door extension and that measured 480 mm wide.

    Last-window-framed

    Last-window-framed

    The next job was to cut and frame the three doorways. They would need a height such that the top of the doors is the same as the windows so the calculations for this resulted in pieces of the timber to be 2252 mm long. We pulled out 3 lengths of our treated 89mm CLS timber and chopped them down to that size, but we noticed one of the timber being rather warped so we fetch’d another length from the pallet! We drilled 4 fixing clearance holes in each of the timber pieces, a clearance 8mm hole for the 100mm concrete screw and 3 x 5 mm holes for the ordinary 80 mm wood screws.

    Taking the 6 pieces out, along with the SDS drill, spirit level, screwdrivers and glue etc. We started with the Great Room-Conservatory French style doorway and fixed and fiddled the two vertical timber pieces into place. It took quite a while for doing all of it, like drilling the concrete holes, getting the spacers in and out and finally getting both sides vertical. We then measured the gap or width of the doorway which turned out to be 1491 mm to 1493 mm in various levels from bottom to top.

    We moved over to the Front Door and repeated everything again and the measurement this time came out at 1495 mm to 1496 mm wide. We were not concerned with this slight difference because these two doors are different styles and both are unique.

    Comservatory-Door-framed

    Comservatory-Door-framed

    Tomorrow, we will finish off the third and final door, the Back Door, and move on to the next job of putting in lintels over all the openings, both windows and doors, all 15 of them!

  • Windows Framework Being Installed

    Today, after our lost day caused by the wet weather yesterday, we resumed our work of putting in the two vertical posts that forms part of the Window frame. We continued on around the building doing each window in turn, putting in spacers to align each post to be as straight and vertical as possible.

    Then just before lunch, we went around measuring all 12 windows and recorded the width at the bottom and at the top. We wanted to know what was the smallest  width and whether we had managed to get the framework vertical too.

    The results are:

    • The smallest width is 1709 mm
    • The largest width is 1718 mm
    • Some windows are not as vertical as we wanted

    So after lunch, we designed and made a template frame that represents the exact width and height of a window. This template was made using 100mm wide strips of the 11mm plywood sheet, all screwed together with diagonal bracing and horizontal ones too, to make a very square and rigid template that is exactly 1708 mm wide between the two parallel vertical edges.

    Window-framing-jig

    Window-framing-jig

    We will use this template, which is now our master reference for our 6 foot windows, to go around each of the 6 foot windows and adjust them so the vertical posts are truly correct and also exactly the same width. This operation is the Real Thing this time around, meaning that we now applied the construction glue to the cement board and the timber to set it in place permanently. We managed to do three windows (Bedroom 3, Bedroom 2 and Bedroom 1) before we stopped for the day and weekend.

    On Monday, we will continue around the Great Room, then the Kitchen and the final 6 foot window on the Entertainment Room. Then we will do the 4 foot windows (2 of them) and finally the single 2 foot window.

  • Friday Mostly Lost to Rain!

    No work outside today as it was wet all morning and occasional showers in the afternoon too. Plus also we were only going to work until mid-afternoon because of other commitments. So the day was mostly written off.

    We did get the stop/start switch on the work bench replaced (it was damaged a few weeks ago), the new switch is much easier to press!

    New-Stop-Start-Switch

    New-Stop-Start-Switch

    Hopefully we can get on doing the windows and doors tomorrow.

  • Window Frames Starts Being Installed and Cement Boards Goes on External Wall to Completes the Circuit

    We had more rain overnight so we decided to leave off doing the last 2 sections of External Wall until the afternoon session. So instead, we started on doing the Window Framework for our 12 windows around the house. Each Window has two vertical posts measuring 1790mm high which will then have a horizontal lintel (made of two layers of 89mm CLS timber) sitting on top of these side posts and two further shorter vertical posts to bridge the gap up to the Top-Plate that is running around the whole wall.

    We first went around to double check the absolute level of each window sill using our spirit level and most were quite flat and level with only some having a 1mm per metre angle error. That is very good!

    So we fetched in 10 more lengths of the treated 89mm CLS timber from our pallet and then chopped them down into the required length in our workshop.

    We started on the Utility Room’s window and using plastic spacers, combined in different layers to provide the necessary adjustment to ensure that both posts were as vertical as possible. These plastic spacers comes in 3 different thicknesses: 1mm, 3mm and 5mm. You can then combine any of these to make any thickness from 1mm upwards.

    We then carried on and did Bedroom 3’s window, around the corner and did Bedroom 2’s window to finish before lunch.

    Window-side-frame

    Window-side-frame

    Spacers-in-window-frame

    Spacers-in-window-frame


    After lunch, we had the delivery of our new sump pump to replace the worn out old pump. So we  spent the next couple of hours installing the new one, including replacing the drain hose pipe with the new 32mm (inch and a quarter diameter) flexible pipe, connected from the pump itself and travels across the concrete and out Bedroom 1 window to then connect to some rigid plastic pipe to go to our rain soakaway downpipe. We will bury this rigid pipework into the sandy soil to keep it out of the way of our building work.

    We had about 15mm of rainwater from the rain showers we had yesterday and the new pump quietly did the job of shifting about 3500 litres of rainwater in about an hour flat! So much better than the old one!!

    The only problem we discovered was that the water would drain backwards once the pump stops so it would fill up the sump hole and switch the pump back on which of course would empty it and .. repeat the cycle again! We didn’t realise that the new pump come without a non-return valve that the old pump had. We couldn’t use the old one because it was designed to fit 38mm connectors (inch and a half) and the new pump takes 32mm (inch and a quarter) connectors, so we had to order on the web a smaller non-return valve.

    The-new-sump-pump

    The-new-sump-pump

    New-pump-in-the-sump

    New-pump-in-the-sump


    Finally, we got to finish off the first line of the cement board on wall “D” and wall “E”. It took only another three sheets to complete the full circuit of the External Wall.

    Walls-D-E-Lower-boards-

    Walls-D-E-Lower-boards-

    Tomorrow, we will carry on doing the Window framework and making additional adjustments to the width of the grouped sized windows, for example, we have 9 nominal 6 foot wide windows, 2 x 4 foot wide ones and 1 x 2 foot wide window. We want to make sure that all these three common sizes are all the same so we can order the same sized double glazing  units and not worry about each window having to be a unique size.

  • Cement Boards Stage 1 Almost All Done

    We had an interrupted morning with the rain coming in, quite a consistent downfall, averaging about four millimetres per hour, for four hours, making a lake of water collected inside our house. Having discovered that our automatic water pump had started making odd groaning and mechanical noises, it seems that it is already worn out only after a few months of operation. So we decided to buy a much better quality pump and a larger bore water pipe to transport the water over to the rain soakaway inlet.

    So We put aside the morning to allow the wood to dry off as much as possible before we started work after lunch.

    We resumed on along the front of the building with wall “A” (the Great Room and Kitchen), did the little sticking out piece of the extension which is wall “B” and then along wall “C” (the front door and Entertainment Room).

    Walls-A-B-Lower-boards

    Walls-A-B-Lower-boards

    Wall-C-Lower-boards

    Wall-C-Lower-boards


    Tomorrow, we hope to get the final two wall sections done (wall “D” and “E”) and we will be back to where we started. After that, we will do the framework for the doors and windows, putting in the lintels etc. before we put on the second layer of the cement boards.

  • Cement Board Skin on External Wall Almost Done

    In the glorious and very hot sunshine, we resumed the task of covering the External Wall with our 10mm thick cement boards.

    But first, as instructed in our approved structural drawings, we took a couple lengths of 63mm CLS timber and cut them to fit diagonally inside the “O” wall to help increase the racking strength. The Great Room extension needs this extra stiffening support because the prevailing wind can blow down across the garden and hit the side of the very long stretch of the Great Room (this is wall “P”) and consequently exert a large load on the extension and twist it sideways, hence why the extra bracing.

    Diagonal-Bracing-on-wall-O

    Diagonal-Bracing-on-wall-O

    After we had done wall “O” with the above job, and also making sure the Legs were all mostly vertical too, we did the same for wall “N” and wall “M”, pulling them sideways a bit to align the Legs to point more vertically. And also later on, doing the same for wall “P” too. We had to tie down bracing lines to pull and hold the adjustment separately on these walls, moving on when we had put up the boards.

    At last, we carried on mounting up the cement boards on “M” wall (Bedroom 1), turning onto the little side wall “N” (the extension of the Great Room), continued around the end of “O” wall and finally completing the longest wall “P” going all the way from the back of the house to the front, this being wall “P”.

    Wall-M-Lower-boards

    Wall-M-Lower-boards

    Wall-N-Lower-boards

    Wall-N-Lower-boards


    Wall-O-Lower-boards

    Wall-O-Lower-boards

    Wall-P-Lower-boards

    Wall-P-Lower-boards


    To finish off the day’s work, we got two spare lengths of 89mm CLS timber pieces and cut them down to size to fit the very front corners of the Front door extension (these being the corners where wall “B” meets wall “C” and again for the corner where wall “C” meets wall “D”). We glued these posts in now so we had something solid to nail up our cement board when we come to it tomorrow.

    Tomorrow, weather permitting, we will carry on along the front of the house which is fairly simple and we will be finished .. for this time around! Next job would be to insert all the additional timber framework to form the windows and doors, before we do the second strip of cement board around the house again.

  • Rain Stops Work

    We discovered the rain was falling down when we wanted to start work on the new week, and the forecast had a high chance of more rain all day so we called it quit and did other tasks unrelated to the building project.

    Tomorrow, the weather looked much better so we hope for a good day of work.

  • Cement Boards Continues around External Wall

    Today, we resumed our task of nailing up the 10mm thick cement boards onto our External Wall framework.

    After bringing all the tools out for this operation, namely, compressed air work tank, nail gun, glue gun, battery circular saw, cold chisel, two routers, electric cable, ruler, spirit level and several other bits and pieces, plus a heap of nails and a clutter of glue tubes too! We went off to load 10 more sheets on our large trolley and wheeled the stack around to the space between the Garage, Swimming Lane and the corner of the house. here we put another one of our portable table to keep the tools handy nearby for the cutting the tongue and grooves edges.

    Tools-for-doing-boards

    Tools-for-doing-boards

    We proceeded to finish off the last section on wall “H”, turning the corner to run along wall “I”, “J” ..

    Walls-H-I-Lower-boards

    Walls-H-I-Lower-boards

    Walls-J-K-Lower-boards

    Walls-J-K-Lower-boards


    And then along wall “K” which is a longer stretch going past Bedroom 2 and running parallel with the swimming lane and finally turning to do wall “L”.

    Walls-K-L-Lower-boards

    Walls-K-L-Lower-boards

    You may have noticed that each of the corners has overlapping sticking out boards and this is deliberate as we will trim off the overlap later and make a neat sharp corner.

    On Monday, we will continue on wall “M” (Bedroom 1), around onto wall “N”, wall “O” and wall “P” which are all part of the Great Room. But first, we must adjust the verticality of wall “N” and “O” before we nail up the cement boards, or we will be in trouble – smile!