Category: Phase 1

  • Earth Tubes Day 1

    The deepest job so far and probably ever, is installing the Earth Tubes! We want these to be buried as deep as possible to take advantage of the cool and almost constant thermal storage of the “earth” at those depths!

    Day 1 – Friday 6th August

    Marking out all the trench lines by banging in 25 stakes around the outside to form a cat cradle pattern!!

    The strings showing where the earth tubes will go

  • Garage site clearance Day 4 & 5

    Day 4 – Thursday 5th August

    Started the day by doing a repair on the digger which I had been meaning to do for ages. The switch which allows the boom to be swiveled side to side relative to the cab hasn’t worked for ages. Fixed it but it took hours… Then back to the soil moving.

    Oops! I bent the wheelbarrow which was leaning against the bank (the boundary between us and school) and backed the dumper truck into it!

    Day 5 – Friday 6th August

    Last bit of soil removal and a bit of a tidy up. Then we could start marking out where the earth tube tenches will go. 25 stakes later a cats cradle was born…

  • Garage site clearance Day 2 & 3

    Started moving the top soil to our spoil heap at the top of the garden. Just load and dump over and over again…

    Day 2 – Tuesday 3rd August

    Day 3 – Wednesday 4th August

  • Garage site clearance Day 1

    The next job is to clear the area for the garage, earth tubes, rainwater tanks and soak away. We need to remove the top soil over the area from the fence to the loke.

    Day 1 – Monday 2nd August

    Remove  paving slabs from in front of the old shed doors. Then at 12:30 Rain stopped play (oops I mean Work!), a nice summer thunderstorm of rain and hail which droped 11mm of rain in 15 minutes! Then the rain set in for the rest of the day…