Number Three Module All Done!
The “Number 3” Energy Module has been completely buried and all finished. The three set of conduit pipes were inserted and connected all together in a central point, so that…
A DIY Selfbuild by Stephen, Shaun & Daphne
The “Number 3” Energy Module has been completely buried and all finished. The three set of conduit pipes were inserted and connected all together in a central point, so that…
This afternoon, Stephen performed some basic maintenance tasks on the mini-digger and loaded grease into all the joints and moving parts. The digger needs re-greasing fairly regularly, every 20 “clock”…
Stephen replaced the old defunct Engine Stop knob on the dumper truck with a shiny new one! It was a relatively simple job and took about 30 minutes. It is…
this morning (only), we half buried the Number 3 Energy Module and put on the insulated lid. We sliced off all the edges and dumped the pieces in and around…
We have assembled the third set of our collection of Energy Modules today, the second biggest one! We put down two layers of insulation boards, a total of 240mm thickness…
It was a long day of cleaning our Aquacell crates we need for Energy Module Number 3. Like before, each one had to be split apart and then each half…
We finished digging out the third hole. We then inserted two parallel wooden side rails into the ground, set exactly at the required depth (minus 1.7 meters below ground level)…
Our old dumper truck wouldn’t stop when the stop button was pulled – a real ironic case of a Stop button causing a Stoppage! The cable from the spring loaded…
For the start of the week, we started on Number 3 Energy Module this afternoon (having had other commitments in the morning) by marking out the boundary of the hole…
Today, we finished off the 2nd Energy Module! We put on a lid of PU foam boards of a variety of thicknesses (90-120 mm) and we used the off cuts from…