Category: Ground Floor

  • Equipment / Machine Sound Absorbing Cupboard Half Constructed

    At the beginning of the week, we finished off preparing the Utility Room by concluding the task of putting up OSB wall boards around the door and then trimmed the window .. well we eventually managed it .. slowly! The router bit we had is getting rather blunt so we ordered some more replacement cutters, nice and sharp! Afterwards we extended the height of this wall board layer inside the window area so it goes up to the level of the worktop by using a whole series of biscuit joints around the three edges and sliding in the new piece from above and then fixed in with PU construction glue.
    Next, we proceeded to cover all this OSB material with Fermacell boards which was a simple process of spraying lines of PU glue foam all over the surface and then staple each piece up with 25mm long staples fired from our compressed air stapling tool. The joints between pieces were stuck together using the thicker PU construction glue instead, to achieve a tougher and stronger joint.

    OSB-on-window-wall

    OSB-on-window-wall

    All-walls-have-fermacall-applied

    All-walls-have-fermacall-applied



    That pretty much concluded the preparation work in getting the basic room done enough so we could start constructing the next object, namely an equipment come machine cupboard to hide away all the various devices, gadgets, mechanisms and storage that will provide the Utilities for the whole house and garage. It is essentially is a room within a room and we are constructing it using thick/heavy materials to try and reduce the noise levels as much as possible and not disturb the rest of the household. So we decided that we would have a cupboard the complete width of the room, from floor to ceiling, along the “E” wall and it will be 600mm overall deep including the wall thicknesses. Part of this design criteria was that we did not want to encroach too closely to the window, to give the window a better look and also we selected 600mm because we didn’t want to have a pile of waste pieces left over when we built the roof out of our 1200mm width sheets. Joining to this basic rectangular shell will be the cupboard region that will hold the clothes drying and vacuum machines, coming along the entertainment wall side of the room and stopping just short of the entrance way to the hall, allowing for the door to open fully and back against the wall. This section is going to be 700mm deep and it turns out to be about 1900mm long, which can be sub-divided into separate modules for each of the machines and other functions like shelving units. This is the extent of what we wanted in creating a noise reducing box like cabinet so we laid down a footprint of treated CLS 63mm timber pieces down on the concrete floor, glued and bolted that defines the outline shape. We also put down extra pieces in front of the window too, to define what would be our worktop and sink section, again being 700mm deep and also being about 1900mm long too.
    Cupboard-Footplates-fixed-down-1

    Cupboard-Footplates-fixed-down-1

    Cupboard-Footplates-fixed-down-2

    Cupboard-Footplates-fixed-down-2



    One of the minor tasks we completed before we continued with the cupboard, was to fill in the joints and corners around the fermacell walls with Polyfilla and smooth it all off so it is sealed. After that, we started building the cupboard using 18mm OSB boards but just before that, we stapled up little squares of foam material that is 8mm thick so that we can maintain a air gap between our new cupboard and the room’s walls, to disconnect any direct transmission of any sounds being generated by motors etc. inside the cupboard.

    We brought a dozen sheets of 18mm OSB inside from our pile outdoors and got them ready. One thing we wanted to do was to use a tongue and groove joints so they formed a solid structure, a backbone for the rest of the cupboard to be built from. Also, we needed room at the top of these walls to fit a “lid” on top and still be separated from the ceiling, this meant that we needed a full height board (2440mm high) plus a narrow strip of 270mm wide to start at the bottom line sitting on the newly installed CLS footplates. So sliced up two board into eight narrow strips and then cut a set of tongue edging on four of them plus groove edging on the other four.
    We proceeded with the narrow strip first, right around outer sides of the cupboard and then put a row of horizontally mounted full sized sheets, again with a set of tongue and groove edging. The long side of the cupboard (against the “E” wall) is 3740mm long so we put in a full sheet in the middle and filled in the left and right ends with 650mm pieces. We were making sure that no joints lined up with each other and creating a stronger monolithic backbone. The top line of OSB board had to have a large section cut out to make way for the air ducting sticking through the wall. Oh yes, the same for the five other sticking out conduits and pipes at various places and also we had unscrewed and lifted the air duct that is coming down through the ceiling.
    we ended up with the first layer all done, starting about 300mm from the window, coming along the “E” wall some 3.7metres and turning along the entertainment wall another 2.5metres before finally turning right angled from the main wall to form the end of the cupboard which is a further 750mm wide.
    First-row-of-OSB-for-cupboard

    First-row-of-OSB-for-cupboard


    That took a while to do because of all the tongue and groove edges we needed to cut and fit everything together with glue etc. but once we have done that first layer, we could mount on the second layer much faster because we didn’t need to do any further tongues or grooves again as we had the backbone layer to press against, keeping the joints neat and tidy. We proceeded to spray a zigzag line of PU glue foam all over the surface and screwed this second layer straight on to the first layer. We had drilled clearance holes all over the sheet, we did a grid of four rows by six columns, giving us a total of 24 screws to tighten the two sheet together squeezing the glue out thinly. We used about 200 screws by the time we done all the second layer!
    Next, we put up a solid CLS 89mm piece of timber right across to form a lintel for the front of the cupboard to help support the heavy “lid” which will be made of three layers of fermacell sheets.
    All-cupboard-OSB-placed-and-glued-1

    All-cupboard-OSB-placed-and-glued-1

    All-cupboard-OSB-placed-and-glued-2

    All-cupboard-OSB-placed-and-glued-2



    On our last day, we went around fitting in a third layer of material, this time our fermacell “plasterboard” sheets, again, just went straight up onto the wall surface with the PU foam glue and this time, was stapled on with 25mm staples. It didn’t take very long and we finished off the day by putting four vertical CLS posts, two 63mm ones up against the walls under the lintel, and the other two being 89mm pieces, again fitted under the lintel but this time 800mm out from the walls. All four will help support the lintel and in turn, the roof of the cupboard. The last piece of CLS, another shorter 89mm piece, went along the front of the side arm of the cupboard, also to support the heavy “lid” over this side section of cupboard.
    Cupboard-lined-and-basic-framework-errected-1

    Cupboard-lined-and-basic-framework-errected-1

    Cupboard-lined-and-basic-framework-errected-2

    Cupboard-lined-and-basic-framework-errected-2

    Cupboard-lined-and-basic-framework-errected-3

    Cupboard-lined-and-basic-framework-errected-3

    The-whole-cupboard-is-isolated-from-the-wall-of-the-room

    The-whole-cupboard-is-isolated-from-the-wall-of-the-room



    Next week, we will start building the lower sections of the front parts of the cupboard, up to the floor levels and getting ready for the flooring supports for the room and starting to lay out the pipework and ducting etc. going across the room and out into the hallway.

  • Preparing Utility Room so Ready to Build Equipment Cupboards

    We arrived for this new week to resume our work on preparing the Utility Room, to get it ready for installing the vast collection of equipment, tanks, switches, pipes and many other bits and pieces that will provide the services like water, air, electricity, vacuum and other utilities.
    We got going on dealing with the black plastic that is pinned up on the wall, covering the window so that got sliced and wrapped down the sides. We also inserted the plastic liners for both the bottom and top cavities that sits below and above the window too. We are just repeating the same procedure as we had done for Bedroom Three windows and these cavities are designed to provide space for the mechanism to control the automatic window blinds. As part of dealing with the window, we put in the extra pieces of CLS timber to frame on all four sides and then put up two vertical 11mm OSB boards on the left and right sides but only after we remembered to install several lengths of 20mm black conduits. We nearly forgot to put one conduit in to allow us access and the ability to feed through whatever electric wires we would need for the mechanism. It was a tight squeeze to slip the conduit behind the plastic already up on the wall but we made it. As part of putting up the plastic and wrapping it into place, we used our malleable white tape to seal tight all the conduits poking through the plastic but also did the large air duct boxing too.

    Next we did the doorway. We had to take off the door again plus all its equipment like electronic lock and sensors etc. so we could wrap the plastic up and onto the door framework, to ensure that we are creating a good vapour barrier. We also put on three extra CLS 63mm timber pieces around the frame that will form the inner surface wall and door entrance. We remounted the door, changing the hinge position slightly and put back all the door furniture and reapplied the door hook too.

    Dorr-framing-redone-and-door-rehung

    Dorr-framing-redone-and-door-rehung


    Looking at the order of things, we then got on with installing the ceiling covering. We needed to do the ceiling next because we are planning to build the equipment cupboard and that will go from floor to ceiling almost and we wanted to put up one layer of the fermacell (this is like a plasterboard material but highly accurate and engineered gypsum mixed with recycled newspaper and no paper liners) to improve the sound proofing levels to stop the machinery and equipment we are planning to employ from disturbing the rest of the household, especially the living spaces up on the First Floor. So towards that goal, we built a second air ducting but this time, it is coming down through the First floor joist structure. We used more of our 18mm floorboards chipboard material to create an oblong shape measuring 600mm long and 240mm wide, narrow enough to fit between two joists and also enters cleanly into our equipment cupboard too. We made it 370mm tall, enough to traverse through the first floor floorboard and joist space. Next, we lined up the box against the floorboard to mark where we want our hole and sliced our way through. This will allow the exhaust air that is being all collected upstairs and being routed around to this spot, to be diverted downwards into our equipment cupboard, to be processed and then rejected outside. We only screwed in this air ducting for now because we can see that we will need to move it out of the way when we come to build the cupboard later on.
    Air-duct-down-from-first-floor

    Air-duct-down-from-first-floor


    Before we can mount our fermacell boards up on to the ceiling, we need to cut a set of tongue and groove into selected edges. We discovered way back when we built the Garage that we couldn’t keep all the sheets of fermacell dead level to each other, even though we put on PU glue and fixed little screws in the joints to hold them steady while the glue dried, it came out very slightly wobbly and it took a great deal of sanding to get it smooth again. So back then, we tried cutting a tongue and groove into the fermacell and it worked like a treat. So today, we took that experience and set up our two router machines with new cutters, both are identical shaped cutters, that does both a series of tongues and groove within the thickness of the material. These cutters can do up to 25mm thickness but we are only wanting to do either 10mm for the fermacell boards and 18mm for our OSB boards.

    We also adapted the two router machines by extending their bases to a much larger supportive area so the heavy machines won’t tilt off the edge and we can pull it along against the surface and the fence, to get a smooth, regular and neat cut. The only different between the two routers is to the exact position of the cutters, one will do the grooves and the other one does the tongues.

    Router-with-extended-base

    Router-with-extended-base

    TG-cutter-in-new-base

    TG-cutter-in-new-base



    It took a little while to do these modifications and testing sessions but it is well worth the time, in order to get good quality results in the long run. So with these new tools, we proceeded to put up a set of fermacell 10mm thick boards up on the ceiling, using our very handy and strong board lifting contraption (It’s a bit rusty from being stored in a shed for 10 years). It runs on highly adjustable wheels so it can squeeze into corners and go around obstacles. But before we did that, we loaded the joist space with a load more of 200mm thick glass wool material to provide more sound proofing.
    Insulation-in-the-ceiling

    Insulation-in-the-ceiling


    We, and our lifter (each full size board weighs 25kg each!), did a row of boards, some 1200mm wide strip next to the “E” wall and then did a wider 1600mm strip along towards the door entrance into the hallway. We did this much of the ceiling because our equipment cupboard will go along the “E” wall and also along the Entertainment wall and stop about a meter before the hall door. We put spray PU glue on the joist flange itself and construction PU glue into the groove to joint two sheets together and plenty of 35mm long staples to fix the board up for the long term. The roof will be inaccessible after we have built the cupboard.
    Board-lifter

    Board-lifter

    Holding-up-a-board

    Holding-up-a-board



    After dismantling the board lifter, we then tackled the “E” wall and covered the entire surface with more fermacell, from concrete floor and right up to the ceiling. We had to put up three and a bit sheets along the upper wall plus a narrow strip along the bottom to cover up the plastic.
    Before we put up the last piece at the bottom we had to remove the very old ‘chimney’ which protected the entrance tunnel for the air from the earth tubes. This just pulled out of the hole in the floor and we had a peek down the tunnel because we didn’t actually know if the tunnel was OK.
    Top-the-Earth-Tube-tunnel

    Top-the-Earth-Tube-tunnel

    View-along-the-tunnel

    View-along-the-tunnel



    This layer, and the one on the ceiling too, will provide additional fire protection too, making our wooden house that much harder to catch alight if we ever had a fire as the Utility room is the most likely place to catch fire in the first place. We will put in extra measures when we build the equipment cupboard and there would be active fire suppression devices installed inside, plus plenty of alarms so we are fully aware when there is a problem.
    E-wall-boarded

    E-wall-boarded


    Now we moved around to tackle the Entertainment wall which is a stud wall made of 89mm thick CLS posts, we only wanted full board of OSB beside the hall entrance so we nailed up narrow strips of OSB pieces on the rest of the legs. We did have to pull off that full sized board because we forgot to put in the glass wool material first! So we duly put in more 400mm wide strip of the 200mm thick glass wool and stuffed them into the 89mm space, yes 200mm into 89mm! This will obviously compress the wool down when we put the series of board on the wall and this is great because it will reduce much of the sound and noises coming from the Utility Room and entering into our Entertainment room where you may be watching and listening to a movie and the last thing you want is, to hear the washing machine spinning or the vacuum system whirling away!!
    So this wall had a layer of fermacell put on, compressing the wool down and this finishes off this wall completely too. Again, we did this now because of our equipment cupboard which will be built slightly removed from these walls to provide another air gap for sound insulation.
    Entertainment-wall-boarded

    Entertainment-wall-boarded


    You may have noticed that we are putting these boards directly onto the wall posts and not on any horizontal rails. This is deliberate as there is hardly any needs for having electrical sockets or switches. Most of the Utility Room will have cupboards, cabinets and shelves and they will have their own electrical sockets inside these regions and nothing will be visible. The only exception is the little length of worktop in front of the window for a sink and we might put up a socket on the side of the cupboard at the end of the worktop.
    The last bit of work for this week is putting up the first layer of OSB board along the “F” wall, to cover up the plastic and provide a strong screwable surface for mounting anything up on the wall, like a worktop! We got as far as the door, again each piece was cut to give a tongue and groove edging to bring together each piece in a nice smooth finish, ready for the layer of fermacell to go on too.
    Window-wall-OSB-started

    Window-wall-OSB-started


    Next week, we will finish the OSB around the door, trim the edges and then put up the fermacell to get that finish. After that, we will start building the equipment cupboard which will be fun!

  • Preparing Utility Room

    One of the first jobs was to move the existing electricity control board from over beside the window and position it out of the way on the dividing wall between this room and Bedroom Three and reconnect some of the electric cables so they were all out of the way before we could fill in the walls with rock wool and cover it up with the vapour barrier. We also did some extra lighting for our hallways, see Installed Lighting Along Hallways. We then started preparing the Utility Room to be created with all its equipment, pipes, valves, pumps, tanks etc. that will serve the house and one of these items was to create an air outlet vent that will allow the exhausted air to escape the house and we did this by chopping our way through the 200mm thick foam insulation near the ceiling and near the left side of the “E” wall as you stand inside the room. The hole we made was the full width between two wall legs, some 550mm wide and a height of 600mm, reaching the cement board outer skin layer where we sliced a 450mm wide by 500mm high hole through the 10mm thick board. We had some stainless steel woven mesh (left-over from replacing our filter in the rain water filtration system), the mesh is woven with fine wire and has 2mm holes which should stop almost all insects and animals from entering the dangerous zone of a fast spinning blades of the air fan. We used some MS Polymer black glue to attach the mesh to the inside surface of the cement board and held it in place using a plastic covered piece of OSB board with clamps to keep it firmly pressed tight while the glue cured.

    Gluing-the-HVAC-exit-vent-mesh

    Gluing-the-HVAC-exit-vent-mesh


    Next, we took some of our left-over 18mm floorboard chipboard material and created a box that will form a large square duct that will help guide the air out of the building. It measures 450mm by 500mm to match the hole through the cement board and put on a ring of 50mm wide strip to provide a larger surface area to bond to the outer perimeter of the wire mesh. The whole box extends well beyond the thickness of the wall so we have options to how much we need when we connect the rest of the ducting and fan later on. Talking about the fan, got one of our new 300mm diameter fans and temporarily seated it inside the new vent hole and powered it up. We did some test runs with different air flow rates and went outside to listen to how noisy it was. We even got out our sound level analyser and took some readings. So at maximum air speeds, we were getting a reading of 63dB at a distance of about 2metres and 65dB and 68dB using different settings on the analyser, representing different patterns of sound pressure and frequencies. The background noise at the time was 40dB, it wasn’t very windy at the time. These figures are quite loud but this was for the maximum possible speed and the sheer power of the fan is that we will only need that kind of air flow rate during the very hottest times of the day in the middle of Summer. Most of the time, the fan will be running much more slowly and we think that it will be about 50dB which is a quiet murmuring noise that fades away when we moved some 5 metres away like the front door or out in the Loke.
    Oh yes, just to make clear, the outside layer of Larch timber was still there, the air was escaping through the gaps between all the planks and it seems to be working very well. It gives us the benefit of having somewhere for the exhaust house air to escape but not having a ugly large metal grill visible.

    So upon the good test results of running the fan, we proceeded to glue the wooden box ducting into place and filled around the edges with more foam boards, using PU spray foam to stick the whole lot together.

    HVAC-Exit-vent-1

    HVAC-Exit-vent-1

    HVAC-Exit-vent-2

    HVAC-Exit-vent-2



    The next job was to insert a long awaited conduit that needed to go from the concrete floor level and all the way up to the Eves, to provide a water irrigation supply for any hanging plants etc. We positioned this conduit near the copper water pipe already installed some weeks ago. There were a couple of other conduits that we also extended and positioned so they were poking out into the room, these were the mains socket in the wall and a couple of underground connections too. Another little task was to screw and glue a vertical CLS post in the corner, the E-F corner to provide a mounting leg for the wall boards when they go up later.
    Because the Utility Room has lots of cupboards, a worktop and the door and window too, this meant that there was virtually no where to put sockets and other switches etc. so we decided that we didn’t need to employ the same design of creating a Utility Channel running around the whole room. It is a bit ironic not having one of these channels, called a Utility Channel, in our Utility Room! Oh well. We did realise that we would like a switch beside the Side Door entrance so we could activate the lights or trigger the garage doors to open if we were going that way, so we embedded two short CLS pieces between the wall legs that is sandwiched by the door and window, to form a pseudo Utility Channel. Oh yes, We remembered to insert another piece of conduit that went down to the concrete!
    Another preparation task was to go around and plane off all the little sticking edges of the plywood that formed the wall leg structure, there are three of these plywood pieces for each leg and some of them are proud of the leg itself and we need it to be all smooth and ready for the wall boards to go up next week.
    Another job that needed doing was measuring and making horizontal rails for the bottom and top of the window and the top of the door too. These rails are the exact position that defines the height and hole of the window at 500mm from the floorboards and 2200mm at the top, also the same for the door too. But we don’t have the same utility rails that other rooms have, we had to fit them inside the framework instead and there is already pieces of CLS timber in place but only approximately at the correct position. We needed to create a special piece for the window, a 45mm to 47mm high piece for the bottom rail and a more even 30mm piece at the top. The doorway was easier and a normal 63mm piece went in straight. Well perhaps not easier after all, because we discovered that our temporary door was too tall and hit this new framework piece. This led us to having to deal with the door itself next. We took it off and decided that while it is off, we would go ahead and install a new temporary door sill, to make sure that we will get above what will be the new floor surface when we put down the floorboards. We found a piece of “4by2” treated timber, cut it down to 1040mm length, to fit the width of the doorway, levelled it off by using a couple of solid 5mm plastic spacers and a smaller 3mm one in the middle and fixed it into place using three concrete screws plus a heap of MS polymer glue to seal the outside joint to provide some water protection against future rain floods.
    Temporary-side-door-sill

    Temporary-side-door-sill


    Now that we had the new sill in place, we could measure the amount of material we would have to remove at the bottom of the door, some 45mm in total. We put in an replacement CLS frame to ensure the bottom of the door was still reasonably stiff. Then we chopped off 10mm off the top to clear that new upper rail and then put the door back. We did have to do further adjustments by running the planer across the bottom edge as the door turned out not to be exactly square but since it is only a temporary door, we kludged it to get it to fit without scraping!!

    Finally, we were in the position to do the next stage of filling in the walls with glass wool and the plastic vapour barrier membrane. We scrubbed the aged timber surfaces along the bottom, applied a line of the butyl heavy duty double sided sticky tape along the bottom edge, around the window and along the top edges too. Where there were a plastic layer already, we used acrylic sticky tape instead. Next, we unrolled and cut up lengths of glass wool pieces, 100mm thick stuff for the lower half and longer pieces of 200mm thick stuff for the upper sections. We filled in the corners and around the door and window so everything is now filled in.

    Fibre-in-utility-walls-1

    Fibre-in-utility-walls-1

    Fibre-in-utility-walls-2

    Fibre-in-utility-walls-2



    After that, we put on sheets of plastic to encapsulate the yukky glass wool stuff and provide a vapour barrier to stop condensation from forming in the body of the wooden walls and hence avoid potential rot problems.
    Utitlity-walls-with-vapour-membrane-1

    Utitlity-walls-with-vapour-membrane-1

    Utitlity-walls-with-vapour-membrane-2

    Utitlity-walls-with-vapour-membrane-2



    We now have finished covering up the walls, just a little bit to finish off like sealing around the air duct and various conduits sticking out, plus finishing off the window and door too. Then we can install a layer of plasterboard to cover up this plastic to provide a fire resistant barrier and then we can start on building the internal “cupboards” that will contain the equipment that provides the utilities and services for the house.

  • Temporary Lighting Installed Along Hallways

    With the days drawing in and as each room is completed, less and less daylight is reaching the inner hallways and they are getting gloomier and gloomier plus also part of moving everything out of the Utility Room, sorting out the wiring, we decided that the hallways on the ground floor needed additional temporary lighting installed. We had a collection of small 10W LED flood lamps, eight of them in all, and proceeded to distribute them evenly around our four lengths of hallways. We used some old 1mm twin and earth lighting cable to join each one up and connect the tail end back into the light switch beside our side door.

    Temporary-hall-lights

    Temporary-hall-lights


    We now have a brighter future in our hallways!

  • Started Work on Building Flooring Structure for Ground Floor Rooms

    We started the new week, after completing our staircase in just four days, by fixing up the metal joist bracket to the stringers at the top of the stairs. We had already made two triangle wedges and they were glued in on Saturday. The metal bracket was only screwed up this time because we want to have the possibility of moving the whole staircase when we come to install our stair lift module later. We are not sure yet whether we will have enough space either side of the stringers to mount cog wheels and other materials to build the parts of the stair lift. So the joist bracket are just screwed on and not glued ..yet!

    Bracket-holding-up-stairs-1

    Bracket-holding-up-stairs-1

    Bracket-holding-up-stairs-2

    Bracket-holding-up-stairs-2



    So onto the flooring job, we got out our green laser line generator and sat the device in the middle of the crossroads of our hallways and adjusted the height until we got the green line shining right on the 10metre mark, this being our Ground Zero line. We already had an 11metre mark on the metal leg “number 5” that is our reference point for the whole house so we measured down one metre for our ground zero, this will be our flooring level for our ground floor. We now have marked all the doorways (Kitchen, Great Room, Bedroom 1 & 2 & 3, Entertainment and Utility rooms) plus every other wall posts everywhere in range from the hallways, also doing the smaller rooms (toilet, tech and knick-knack cupboards etc) plus the front door and stairs too. We want to be able to place our laser line generator in each room separately and get the floor height exactly the same all over the house when we get to do that room.

    One of the first things we needed to do, after doing the laser calibrations, was to empty the content out of each room we want to work on, so in Bedroom 3 we had to move our solar water tubes and a heap of ladders etc. so we decided to move them, the solar tubes to our new storage area, mainly the first floor and its great expanse, to get them out of the way for the time being. But first, we felt the need to be a bit careful and clever, to position these items upstairs so they don’t impact too greatly on us working upstairs like building walls etc. To this aim, we marked out an outline of each room and their walls, these being the Creative room, the Study, the Workshop and the toilet plus all the “triangular voids” spaces and the large storage space behind the toilet over the top of the back rooms of the house.

    First-floor-rooms-marked-out-1

    First-floor-rooms-marked-out-1

    First-floor-rooms-marked-out-2

    First-floor-rooms-marked-out-2



    Then, we moved the six crates that holds our one hundred solar glass collector tubes from Bedroom 3 to upstairs and placed in the Study over the Entertainment room and front door. The heap of ladders etc. were moved to sit underneath the new staircase.
    This meant that we could and did get on in constructing the flooring for Bedroom 3 (the one next to the Utility Room) and got the laser to shine a green line right around the room, aligned to the reference marks at the doorway and carefully marked all the vertical posts and stuck masking tape on the black plastic to see the mark there too. Then slicing five lengths of our usual 63mm CLS timber, we nailed up a perimeter of a support framework that will hold the 22mm thick floorboards when we are ready for them to go down. The room is arranged in a grid pattern with 600mm spacing between the contiguous joists and an alternating noggings in every 1200mm in the opposite direction.

    We built a little laser hanger gadget that hooks on to the perimeter rail so the green light will be exactly the height of all the legs supporting all the joists and noggings. We cannot just simply measure the distance from the concrete floor surface, up to the underside of the CLS joist because both the concrete floor and the wood slowly rises and dips in random directions, hence this little clever hanging gadget to position the laser line generator to shine its green line against each set of legs to be trimmed.

    Laser-marking-leg-heights-1

    Laser-marking-leg-heights-1


    We are using our left-over treated timber for our legs, plus dipping the cut ends into more preservative treatment, all to protect the wood from rot if we ever got a flood under our floor, we don’t want to find that our flooring supports started rotting after a decade or two and find our floor sagging. So we are dipping the cut ends into a trug that has black died preservative and therefore we would know which end to put downwards.
    But these little legs are only 63mm wide (by 38mm in the other dimension) so aligning the leg underneath the horizontal joist (which is also 38mm thick) would poke out only by 25mm. This is plenty enough to support noggings but only on one side at a time. This means that we staggered the noggings in each row so the whole room is evenly supported across the floor.
    Bedroom3-Floor-supports-in-place

    Bedroom3-Floor-supports-in-place


    The next job was to sort out the bundle of water pipes and cable conduits that runs across the room, from the external walls, from underground and passing through from the Utility room. We did the hot water pipes first which comes along from the Utility in 28mm pipes and curves towards the en-suite. We had always planned to have 28mm diameter pipes, to hold a high volume of water flowing throughout the house and also we wanted to constantly keep this hot water supply hot and active, ready for any demands. This means that we have two hot water pipes running alongside each other, a “flow” and a “return”, just like in a traditional central heating systems. But we recognised that there could be a good deal of heat loss, and money, in a constantly circulating system, losing energy around the loop all the time. So to this issue, we put down two layers of 100mm thick PU foam boards, sitting on the concrete and cut a slot in the top of the second layer for the 28mm pipe to sit snugly in.
    Bedroom-3-Hot-water-pipes-layed-in-insulation

    Bedroom-3-Hot-water-pipes-layed-in-insulation


    Then a 90mm thick “lid” went over the top that brings it up to the underside of the wooden floor supporting framework. The rest of the space on either side will also be filled in with more insulation so this hot water system will be as protected as possible against heat loss and provide our whole house with quick supply of hot water when we want it.

    The cold water is also supplied in a 28mm diameter pipe but that is running “loose” nearby the hot insulated pipes and all three are routed to arrive just outside the en-suite doorway where we will have a liftable panel cover to gain access to the various controls and devices to condition and supply the water needs for the basin and shower in the en-suite. We built an extra framework around this area to support the “lid” and also inserted vertical PU foam boards to act as a barrier to keep the loose insulation in the rest of the room from “leaking” into our inspection and servicing chamber.

    Then we connected up more water pipes, this time in 15mm diameter pipes that connects to our Energy Module (a buried tank of water), a pair of them so we can exchange the energy (hot water) from the tank to the Utility room and back again. the pair goes into conduits that were fitted to provide a “high” and “low” extracting points so we can draw off the floating hot water and put in new hot water down in the bottom of the tank. These 15mm pipes are only intermittently used so they don’t need a great deal of insulation, just the normal floor insulation to keep it warm while it is being transferred to and from the Utility room. The other 15mm pipe going into the Utility room is a connection to our Swimming lane. We did an external connection (drilling through the concrete wall) several months ago and so we laid in this pipe too. This Swimming lane connection will provide a source of cold water to help “sink” any excess heat away. The Swimming lane is a 25,000 litres of reasonably cold water to make use of!

    The final 15mm water pipe is also an external connection but this time, it is a low-volume irrigation watering system to serve the garden in and around the this end of the house and this 15mm pipe only needs to travel to our servicing chamber we have already made. At this point, a computer controlled water valve will be installed and connected to our cold water supply later on when we have designed and built such devices. The other connections to our servicing chamber are empty conduits, the first two being also irrigating watering feeds but this time up to the Eves for any hanging baskets etc. The final five other conduits snaking across the room are the temperature probes that will monitor the regions immediately surrounding our buried Energy module. All these conduits are 20mm diameter black polyethene pipes and we joined them to the sticking (out of the concrete) up portions using short length of the fatter 25mm polyethene pipe which fits perfectly and very tightly providing a smooth joint and transition for our cables and sensors when we push them down the conduits.

    Bedroom3-Plumbing-access-area

    Bedroom3-Plumbing-access-area

    Bedroom-3-Conduits-in-floor

    Bedroom-3-Conduits-in-floor



    We are not quite ready to put on the lid or fill the space with the insulation rubbish because we got other tubes to lay in the floor, this time for the air supply. We are going to have four 50mm conduits running from the hallway, next to the doorway, and branching out to the four walls, to distribute the fresh air. We will have a air channel just at the bottom of the walls to spread the air out and enter into the room itself in a gentle flow, without too much disturbance to the feel of the room. We won’t be able to totally avoid any movement as it is meant to be providing fresh air and drawing the old stale air out at the ceiling, just like as if the windows are open on a warm day. Another set of conduits are needed to be laid in, this time to route the electricity cables from one side of the utility channel to the other side, going around doorways and windows. This will be done when our delivery of new twin wall plastic tubing arrives next week.
    In the meantime, we started on the task of nailing up the horizontal wooden rails, we called these utility rails because their function in life is to provide the space for our Utility Channel that goes around the whole room at the 800mm to 900mm height, plus also we are using this separation to allow for the air channel to run around the room too, down near the floor. Each of these horizontal CLS rails (our usual 63mm by 38mm timber) are positioned as follows:

    • 235mm off the floor (air channel)
    • 772mm (bottom boundary of utility channel)
    • 1010mm (top boundary of utility channel)
    • 1703mm (mid support point for wall board)
    • 2422mm (support of wall boards at top of wall)

    These measurements are for the top edge of the CLS timber because we can see it with our green laser light (more later on) and a 22mm offset is also added because we are measuring from the floorboard supporting framework that will have the 22mm thick floorboards laid down later on. We marked the door post with these measurements and then clamp our green laser line generator which is sitting on a small shelf at each measured mark. Then we went around nailing up lots of CLS timber to create the wall framework for holding up the finishing surfaces and of course to provide the space for our electrical sockets etc.
    We started using our left-over timber (a large pile of it in the kitchen) to form these horizontal rails by using a biscuit joint to join smaller lengths together. We also inserted a horizontal rail at the window seat level, this one being 500mm off the floor surface.

    Aligning-a-rail-to-the-laser

    Aligning-a-rail-to-the-laser

    The-laser-bracket-clamped-to-the-wall

    The-laser-bracket-clamped-to-the-wall

    First-three-rails-fixed

    First-three-rails-fixed



    That concludes the work so far for this week and we will carry on next week with the wall support and laying in more conduits when they arrive.

  • Ground Floor Walls Structure All Finished

    We continued the task of putting up reinforced wall posts for the hanging toilets for the cloakroom and for the en-suite of Bedroom 3 where we had to put down an additional footplate inside the knick-knack cupboard, to allow for a box to be built around the back of the toilet pipework and the sewage pipe going down into the concrete. We put another one of our homemade I-Beam element, but a shortened one.

    Then we resumed putting up a forest of posts all around the remaining Ground Floor walls including the cloakroom, linen cupboard (where we put in a double post to support an extra wooden lintel over the doorway), the en-suites and finishing off Bedroom 2 and Bedroom 1.
    Another section that had to be done was in the Great Room entrance way. This point is between the steel legs of the Skylight and it has a large C shaped steel beam (designed to hold up the first floor going over this doorway) and we needed to glue a couple of pieces of timber to the top and bottom flanges. The top one is an ordinary CLS timber plank, a 89mm wide piece but planed down from 38mm thick to 33mm thick to match up with the actual joist support level. The bottom flange however wanted to be a much wider piece, about 200mm in actual fact so we used our 18mm OSB boards and cut off two strips. We glued them together to form a 36mm thick planks and then glued this up on the bottom flange of the steel beam, all clamped overnight to dry and cure. After that, we could install the last set of posts for the ground floor, this time, the edges of the sliding door cavity
    Then the final job was to lay on the two levels of top-plate CLS timber to tie all the posts together, to tie all the walls together and create a another solid set of rooms.

    To conclude this stage of the operation of building the Ground Floor walls structure, we put on the second layer CLS timber pieces all the way around on the external walls and added a third layer across the doorway and window in our Utility Room because these have a major load from the First Floor Joists.

    We finished the week by tidying up all the pieces of cut-offs, the tools and preservative liquid, to make the place ready for the next task. That is probably be installing conduits through our external walls so we can easily feed additional cables etc. from inside to outside when we need lighting or speakers etc outside.

  • All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    We have resumed our task of building up the Ground Floor’s walls, at least, the structural framework structure using our 63mm CLS timber planks and over the last eight days we got quite a long way forward. But one of the first jobs was to redo the vertical timber pieces that were glued to five of our steel legs, we discovered that we didn’t do a very good job in the first place, or rather we hadn’t realised that the primer paint was not very well stuck down as the metal wasn’t very clean when it got painted years ago. So we easily ripped off the timber pieces and then used the angle grinder with a metal scrubbing disc to polish the metal to a nice shiny finish. We also cleaned the timber planks as well using a clean but similar sanding disc and finally applied a fresh coat of PU glue and reattached the timber back to the steel legs.

    The next task was to look at the four wet rooms, the bathroom and the three en-suites, because we wanted to put across the entrance ways, a proper and robust lintel to support the first floor joist without having to need any supporting posts underneath. This feature would then allow us to have the option of having complete glass walls and door for our en-suite or indeed other designs we may come across. We had four left-over pieces of rectangular tubing from our steel legs which hold up the Skylight which proved to just be long enough to bridge over the entrances. These steel legs are 100mm by 50mm with 5mm thick walls so they turned out to be very useful to serve as very strong lintels. We only had to slice very small bits off two of them to make them fit for the Bathroom and bedroom 3’s en-suite. Next, to sort out the pile of 145mm by 45mm timber planks and decide on which ones we can used. We decided that we needed one of these wide planks to help with the lintel and combined with the steel element, will help secure the joists in place and properly transfer the load of the first floor sideways to the posts. These posts are made up of another piece of the 145mm wide timber, coupled with narrower 95mm by 45mm plank we had left over and was sitting in our swimming lane storage yard. So each composite lintel was made from gluing together the steel element with the 145mm wide wooden piece.

    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    Sliding-door-lintels-started


    And then we glued the two wooden pieces, the 145mm and the 95mm planks together to form the integrated post, including a notch cut out to receive the steel part of the lintel. We left that to dry and cure. So in the meantime, we spent a few hours bringing in the first load of CLS timber planks that we have lying outside that was delivered a few weeks ago. We moved about 150 planks.

    The following day saw the new lintels and their posts get fitted and fixed into place, making sure that each one was straight and vertical.

    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    End-of-an-En-Suite-lintel

    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    Steel-lintel-for-Daphnes-En-Suite



    After that, we could carry on in building the stud walls from all the footplates we had put down a month or so ago. We started over in Bedroom 3, making sure that the load bearing elements had studs spaced apart by 400mm and the perpendicular walls had 600mm spaced legs. We went around all the smaller rooms, the the Bathroom, en-suite 3, the Tech and Knickknack cupboards plus one wall (the long wall) of Bedroom 2 and then the corridors including doing two doorways. Finally, we put on the two layers of the top plates, overlapping in each direction to help bind all the section of walls together.
    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    First-few-rooms-are-Framed


    One of the tasks we wanted to do since we were getting on much quicker than we imagined in building these walls, is to find and buy the I-beam joists we would need for building the first floor so we spent one of the mornings measuring all the lengths of various rooms, to make sure that what is actually the real world measurements, matches the technical drawings, before we send off the final shopping list of these composite wooden I-beams. We need 61 in total, about 460metres in all, ranging from 5metres to double that size of nearly 11metres. It was quite good and matched within 20 to 30mm to the drawing but we had always intended to round up the measurements before sending the list off to four local suppliers and one manufacturer. But only two suppliers have replied with quotes in the ball park figure of £2,800+VAT in total, about £6 per metre. This price includes the wastage from cutting the beams from stock lengths and we realised that we could make use of these waste pieces, by slicing them up into shorter lengths and turn into our noggings to strengthen the sideways anchorage of our very long and tall joist hence utilising all the wastage that we would had paid for anyway.
    Then, spread over the afternoon of Friday and the next morning, we finished moving in the rest of the CLS 63mm planks to our indoor storage area. This makes a total of 600 planks we moved this week.
    Added with our existing pile, we now have 772 planks to be used for building the ground floor walls including the horizontal structs, the floor support framework, the first floor walls and ceiling. We hope we got enough!
    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    CLS-All-moved-in

    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    More-than-750-pieces-of-CLS



    For the rest of Saturday, we marked out roughly where all the wall stud posts will go, including making provision for the three hanging toilets, the various doorways like the sliding doors for the cloakroom. There is a total of 86 of these posts to do, to finish off the ground floor walls, of which 25 have their ends dipped into timber preservative to ensure long term survival in these various wet rooms.
    For the hanging toilets, we designed our own I-beams structure, a pair of CLS timber with four pieces of plywood glued and screwed across to make a ladder like combined element. This will help stiffen up the point where the toilets will be mounted and keep everything nice and stable. So between Bedroom 2 and 3 pair of en-suites, we positioned the three of these I-beam elements so each en-suite can have their toilet and connect into the same pipework.
    All the CLS Planks Moved Indoors and Ground Floor Walls Is Going Up

    First-toilet-wall-framed


    They are positioned so that we meet the minimal legal requirement of at least 500mm spacing on each side of the toilet including the bowl itself.
    Next week, we can do the cloakroom in a similar manner and also do the same thing for Bedroom 3?s en-suite too. Then we will carry on putting up the rest of the stud posts.

  • Utility Room reorganised and First Solid Wall built

    We needed access to the sections of the exterior walls in the utility room to get the insulation boards in, we are currently storing tools there. So today, Thursday, on April fools day, we built the first solid wall between Bedroom 3 and the Utility Room to give us more space to store tools. This wall is the usual 63mm thick but we had put on an additional fermacell plasterboard layer on the interior side of the wall, then filled up the hollow space up with 100mm thick glass wool we had lying around in our garden shed, some 10 years old (and perhaps too old as the material didn’t seems to spring back into its full 100mm thickness), to act as another sound absorbing layer. The whole thing was covered up with a layer of 18mm thick OSB board to provide a good solid first layer of sound reducing wall, between Bedroom 3 and the various noisy equipment that will live in the utility, like the washing machine and drying cabinet and the other pieces of equipment for running the air conditioner etc.

    Utility Room reorganised and First Solid Wall built

    First-solid-wall-1

    Utility Room reorganised and First Solid Wall built

    First-solid-wall-2



    Then we moved the Ikea wooden shelving modules over to sit in front of this new wall and unscrewed the electric switchboard off the wall. We then installed the insulation in the walls and re-installed the (temporary) electric switchboard.
    Utility Room reorganised and First Solid Wall built

    Utility-insulated-and-re-arranged

  • New Wall Hanging Toilet and Frame Arrives for Evaluation

    Today saw the arrival of our new toilet and wall frame!

    New Wall Hanging Toilet and Frame Arrives for Evaluation

    New-wall-hung-toilet


    We wanted to see and learn all the construction requirements for these wall-hanging toilets designs, like how the cistern and the metal support framework needs to be incorporated into our wooden walls.
    The Toilet is a rimless design around the bowl but this is a bit misleading, there is still a wide rim (see photo) for the seat to rest upon
    But what they really mean, is the water flushes out and around the top edge of the bowl in a slight groove and then falls into the bowl. You can see the water flow along and that is what they mean by rimless. It is a new fashion and the plus points are that it is much easier to wash the bowl clean and one can see this immediately.
    But on the other hand, it does mean that the power of the flush has to be controlled to avoid the water simply shooting over the edge if it is travelling too fast. There is a controlling valve inside the cistern to regulate this flow rate and yet another piece of equipment that may go wrong over the years.
    New Wall Hanging Toilet and Frame Arrives for Evaluation

    Toilet-hanging-frame-1

    New Wall Hanging Toilet and Frame Arrives for Evaluation

    Toilet-hanging-frame-2



    The toilet bolts onto the Frame which is fixed in the wall and covered with the wall boards.
    We will evaluate this design, by building our cloakroom straight away, plumb the toilet into the sewage system and supply water to the cistern and learn how it all works.

    We will start on this task mid to late January when Shaun has recovered.

  • Remaining Pillars Installed for Corners and Kitchen Wall Framework Finished

    For our last week of work for 2020 (and also before a long break because of Christmas and a minor medical issue), we went around the last twelve Pillars across all the ground floor rooms, creating sturdy accurate corner and T-junction reference pillars, all vertical and straight.

    Remaining Pillars Installed for Corners and Kitchen Wall Framework Finished

    Last-corners-errected

    Remaining Pillars Installed for Corners and Kitchen Wall Framework Finished

    for-bedrooms-and-bathrooms



    We made sure that the metal legs (holding up the Skylight) had pieces of CLS timber glued to them that were also vertical and ensuring that the metal legs themselves are hidden inside the wall structure.
    Then, for the last day and a half, we concentrated on building the framework that surrounds the Kitchen. We positioned exactly where we wanted the sliding door module to go near the Great Room end of the hallway, plus also a narrow window module (we had one left-over window Oak frame that we didn’t use in the external wall) positioned on the same wall but at the opposite end of the room. Then it was a case of slicing many many vertical posts (two sets measuring 2885mm and 2645mm tall) and went around nailing them into place. This included the first layer of the top plate to secure the posts and form the completed frames of each wall section.
    Remaining Pillars Installed for Corners and Kitchen Wall Framework Finished

    Kitchen-wall-framing-complete-1

    Remaining Pillars Installed for Corners and Kitchen Wall Framework Finished

    Kitchen-wall-framing-complete-2



    It is amazing to how quickly a room like this Kitchen can be built, even if it is just an open framework of posts etc., we can already get a feel for the size and shape of each room we have planned for our Ground Floor.
    We are cutting up lots of pieces of wood for the job (over 200 so far)
    Remaining Pillars Installed for Corners and Kitchen Wall Framework Finished

    Wood-cut-so-far


    This concludes the work for 2020, we can enjoy Christmas and New Year and when we are ready, we can resume work in 2021. It is holiday time now!!