Category: Walls

  • Waterproof Bitumen Paint Job Started – Day 1

     Today, we started the task of applying  the bitumen paint to the outside surface of our Perimeter Wall to make it waterproof against damp and floods.

    The morning was spent trying to use compressed air and a spray gun to splatter the black thick heavy liquid from a tank to the wall, but unfortunately, it didn’t work! Even after we tried “Pushing” the liquid down the tube using more compressed air in the top of the tank to help the thick liquid to get into the air spray gun. So that was abandoned and spent the remaining time cleaning the tools with petrol to lunch time! We did do some more tidy up of concrete blocks cut-offs and OSB sheets etc. too! Just to conclude this experiment of spraying, the manufacturer stated on their web site when we stopped for lunch, said that the best way was to use a direct pressurised spraying system like those high pressure washers we used for cleaning cars and patios, but even stronger at 2000psi (pounds per inch or 133 bar (a bar is normal atmosphere pressure) !!) and we were trying to use our 10bar air compressor – no wonder it didn’t work!! Grin!

    So this afternoon, we went to the old fashioned method of brush and a tray and even a roller to apply the bitumen paint (which has rubber dissolved in it too) to the wall. We started on the garage side of the building, in the Utility room and went around towards the swimming lane, along the back of the building and arrived at the far corner in the Great Room. This is just over half way and we have used about ¾ of the first barrel of the paint. This is just about on track to the required coverage as stated in the instructions on the barrel, which we calculated to be 1½ barrels of the bitumen paint per coat for a complete circuit of the wall!

    Painting-walls-day-1-2

    Painting-walls-day-1-2

    Painting-walls-day-1-1

    Painting-walls-day-1-1


    We are going to do 2 coats so tomorrow, first we will finish off the long loop around the Great Room and the front section and then start the 2nd coat in the afternoon and hopefully finish off on Wednesday!

  • Day 11 of Perimeter Wall Assembly and .. It is ALL Done!

     With the rise of the sun  (;-), we started work early today at 9am, it was a very humid and stuffy morning with no breeze to keep us cool. But we got on with the 4th layer of our Perimeter concrete block wall and did 51 blocks before lunch time at 1pm.

    After lunch, with a little breeze and clouds hanging over head, we completed the loop by putting down 56 blocks, our afternoon load of mortar didn’t quite reach the end so we had to mix a small extra quantity to finish off the very last 1¼ blocks.

    Walls-Finished-Internal-Panarama

    Walls-Finished-Internal-Panarama

    Walls-End-of-day-11

    Walls-End-of-day-11


    It was a long day, from 9am to almost 7pm and doing 107 blocks which smashed the previous record, but it was well worth the effort as it is very pleasing to see it all done! So This Concludes the block laying for the concrete Perimeter Wall which took us 11 days!

    The next job is to spray bitumen paint on the outer surface to provide that extra protection against surface water and rising damp from the soil.

    Later when we are pouring the floor slab we will also fill the hollow columns with concrete.

  • Day 10 – Construction of Perimeter Wall

     A long day of doing the 3rd course of the block wall and going onto the 4th layer with our morning and afternoon sessions. The morning one saw us doing 49 blocks and in the afternoon we laid 47 blocks – a total of 96 blocks! A New Record!! Phew!

    First-bit-of-completed-wall

    First-bit-of-completed-wall

    Walls-End-of-day-10

    Walls-End-of-day-10


    We have 104 blocks left to do in the final layer to complete the whole job! We will have to put in a little extra sand into our mortar mix to make it extend to doing those extra blocks. Tomorrow WILL be an even longer day but well worth it as the job will be done at last! We might start an hour early to avoid running late into the evening!!

  • Perimeter Wall interrupted by Rain!

     After lunch, because of the rain forecasted to arrive about 4pm to 5pm which made block laying impractical we had to do something else. So we moved and tidied up the remaining concrete blocks and distributed them around the complete circuit to where they are needed ready for the resumption of work on Monday.

    Blocks-ready-for-final-rows

    Blocks-ready-for-final-rows

    Yes indeed the weather guys got it right, we had the arrival of the rain around 4:30pm!! Grin!

  • Day 9 of Perimeter Wall Block by Block!

    We started early this morning to try and do as many concrete blocks on our 3rd tier of the Perimeter Wall before lunchtime and the predicted rain coming this afternoon. But before laying any blocks today, we marked the walls where the 3 doors will go as there are no blocks in rows 3 or 4.

    Front-door-goes-here

    Front-door-goes-here

    Back-door-goes-here

    Back-door-goes-here

    Conservatory-door-goes-here

    Conservatory-door-goes-here


     The block laying went quite nicely and we laid 49 blocks with the one mortar load. Therefore if we had the afternoon to do more work ahead of the approaching rain (which would ruin any mortar joints done in the afternoon, not having enough time to set), we would have been on course for a new record of just shy of 100 blocks!!

    Walls-End-of-Day-9

    Walls-End-of-Day-9

    Maybe, on Monday, we will get another chance at beating our record when we continue to do the 3rd layer and move on to the 4th and final layer, which in total, is about 210 blocks left to complete our Perimeter Wall – about 2 days of work left to do!

  • Day 8 of Perimeter Wall Heading Upwards!

     We set a new record today of putting down 85 concrete blocks in two sessions! This morning, we carried on with the 2nd layer and completed the Great Room, the Kitchen and started on the front extension by 2 blocks, doing 39 blocks all together. The afternoon session saw us completing the circuit, finishing the front section and the back door side of the building. We put down 35 blocks to join up the circle!!

    Walls-Layer-3-Bedrooms-2-and-3

    Walls-Layer-3-Bedrooms-2-and-3

    Then we started the 3rd level and managed to do a further 11 blocks before we ran out of mortar. This was a total of 46 blocks for the afternoon!! We probably achieved this higher rate because we reduced the amount of mortar we put down on the layer.

    Walls-End-of-Day-8

    Walls-End-of-Day-8

    We have a day off tomorrow, but on Saturday, we carry on with the 3rd level, remembering to leave a gap for the doorways (the French doors in the Great Room, The front door and the side door in the Utility Room). Wonder what record we can break then? Grin!

  • Day 7 of Perimeter Wall Construction, Layer by Layer

     We finished off the 1st layer this morning and then started the 2nd layer around the back of the building (Bedroom 3 and just into Bedroom 2) before lunch. That was 28 blocks in that session.

    Walls-Layer-2-Bedrooms-23

    Walls-Layer-2-Bedrooms-23

    Then this afternoon, we zoomed along Bedroom 2, Bedroom 1 and half way around the Great Room before we ran out of mortar, plonking down a further 40 concrete blocks!

    Walls-Layer-2-Great-Room-Started

    Walls-Layer-2-Great-Room-Started

    Walls-End-Day-7

    Walls-End-Day-7


    That is a total of 68 blocks for the day – WOW!

    Tomorrow, we hope to complete the 2nd layer, doing a further 70 or so blocks, which should be feasible judging by this afternoon’s speed!!

  • Day 6 of Perimeter Wall Rising Out Of Ground!

     Today we carried on doing the 1st layer of the blocks, filling in the straight portions between the corners. Even though we had a delayed start (due to a haircut session!) we still did two loads of mortar, one for the morning and one for the afternoon. We did 49 blocks in total and have completed all the way around the Great Room, Kitchen, Hall and Entertainment room, and almost the front section of the Utility Room.

    Walls-End-of-day-6

    Walls-End-of-day-6

    So tomorrow, Just got the one more block to finish the front wall, and then the long run of 19 blocks to the back and to the beginning of where we started yesterday! We had used quite a lot of mortar for this tier of the wall so when we do the 2nd (plus the 3rd and the top 4th) tier, which will have a much more controlled mortar thickness (a thin 10mm thick instead of a rough 20mm), our mortar will go much further indeed and we may run out of time before the mortar goes off. We will see!!

  • Day 5 of Perimeter Wall Construction

     Today, in a mixture of sunshine and clouds but no rain, we finished off the final 9½ corners to complete the 4 tiers we got designed for our Perimeter Wall, this adds up to 19 blocks mortared in place.

    We then started on doing the straight parts of the perimeter wall, using a new template tool we quickly knocked together to provide a way of applying  two even strips of mortar onto the concrete foundation

    Plus a string pulled tight between the corners to provide a nice ruler  straight line to alight the blocks! We did a further 40 blocks to go around the 1st layer, completing about a third way around. This first level is slower because it needs more mortar and time to make sure it is set properly on the rough foundation strips, but we should speed up once we get onto the 2nd layers and beyond!!

    Walls-End-of-Day-5

    Walls-End-of-Day-5

    Walls-Day-5-

    Walls-Day-5-


    Tomorrow, we resume and hopefully will do about another 50 to 60 blocks and finish the complete circuit!

  • Day 4 – Perimeter Wall Corners Taking Shape!

     Today, under a cloudy sky and swirling winds, we finished off the 3rd tier of concrete blocks, doing 12 corners to complete the loop around the building, each corner having 3 blocks mortared in place.

    All-4-layers-on-first-corner

    All-4-layers-on-first-corner

    Then we sliced off 75 mm off of 14 blocks (see image below) using a diamond disc in the angle grinder.

    Cutting-blocks

    Cutting-blocks

    To start the 4th and final layer our perimeter wall will have one of these shortened blocks in the corner with the cut off piece around the corner. We completed 4½ corners, this time each has 2 blocks!

    End-of-Day-4

    End-of-Day-4

    On Monday, we will finish off the remaining 9½ corners and then we can get on with filling in the straights between all the corners!! Phew!