Sewage Processor is up and running!
This posting is a record of the moment where the air pump was switched on and we had air bubbling through the water! Very Nice! It is now running continuously…
A DIY Selfbuild by Stephen, Shaun & Daphne
This posting is a record of the moment where the air pump was switched on and we had air bubbling through the water! Very Nice! It is now running continuously…
The work continues with the Sewage Processor installation and its connections! Day 3 – Tuesday 13th July Started with the concrete mixing to bed down the processor unit but didn’t…
It’s a Stoppage! The Extension Collar for the Sewage Processor does not fit! The collar is designed to slide over the ring moulded into the top of the tank but…
The final load of concrete is now in early this morning and after a couple of hours for it to set enough, we loaded 10mm gravel in around the sides.…
The new capacitor arrived (rather late in the afternoon !) and installed it in the cement mixer and it’s go go go! Or at least it will be tomorrow! Sharp!
A quick review of our construction of the Leach Field. The video contains all 12 days of our work speeded up by over 300 times normal (one picture every 30…
Day 1 and Day 2 of the Installation of our Sewage Processor! Saturday Day 1 Finished off compacting the soil over the Leach field. The Sewage Processor’s location is calculated…
The work continues .. .. Day 7 – Friday Finished off the sand layer to required depth (700mm). Marked out the trench lines ready for the 40mm stones. Day 8…
We had an email today from Dave, our Building Control Officer, saying that the Structual Engineering report on the Garage design is ok and he is happy so long as…
Dave our Building Control Officer came today to inspect our Leach field and the pipes. He said “OK” and that was that! Painless! So Far! He asked to see the…