Equipment / Machine Sound Absorbing Cupboard Half Constructed
At the beginning of the week, we finished off preparing the Utility Room by concluding the task of putting up OSB wall boards around the door and then trimmed the…
A DIY Selfbuild by Stephen, Shaun & Daphne
At the beginning of the week, we finished off preparing the Utility Room by concluding the task of putting up OSB wall boards around the door and then trimmed the…
We arrived for this new week to resume our work on preparing the Utility Room, to get it ready for installing the vast collection of equipment, tanks, switches, pipes and…
One of the first jobs was to move the existing electricity control board from over beside the window and position it out of the way on the dividing wall between…
With the days drawing in and as each room is completed, less and less daylight is reaching the inner hallways and they are getting gloomier and gloomier plus also part…
We resumed the work on Bedroom 3 with the Wall Boards. We switched over to the tongue and groove method of joining two boards together and it seems to be…
After having finished the floorboards for Bedroom 3, we can walk around much easier and inspect everything. We decided to swop out the cable conduits around the windows with our…
Continuing with Bedroom 3, this week we installed more various elements into the wall and floor structure to provide additional functionality to the operation within the room like, for example,…
We continued with the work on Bedroom 3 and getting the floor, walls and windows ready. Whilst we are waiting for the deliveries, we got on with finishing the windows…
We started the new week, after completing our staircase in just four days, by fixing up the metal joist bracket to the stringers at the top of the stairs. We…
Whilst tidying up the house of the insulation foam rubbish, a new set of shelves was created to provide more room for tools and parts to be on hand for…