The last segment of a trench, the utility trench, is finally dug! All the way to the water meter, alongside the Loke, passing the mains electric cable (a rusty iron clad cables) and the point where the telephone will join into our land.

The trench is 400mm wide and on average 1000mm deep and about 30metres long!

Final leg of utility trench

Final leg of utility trench


Final leg of utility trench

Final leg of utility trench


Final leg of utility trench

Final leg of utility trench

At the bottom of the trench , we have already laid down the water pipe and telephone conduit and later on we will have the main electrical conduit higher up (about 300mm ).

Utility trench with water and BT

Utility trench with water and BT

Tomorrow, weather permitting, we will fill in the first layer of sand and dirt on top of the water pipe and telephone conduit. And then lay in the electrical conduit and finish filling in using the rest of the dirt.

By Shaun