Removal of Builder’s Rubble
We took the opportunity to empty our builder’s rubble we have collected over the last couple of years. We had been loading up two separate ton bags with various rubbish…
A DIY Selfbuild by Stephen, Shaun & Daphne
We took the opportunity to empty our builder’s rubble we have collected over the last couple of years. We had been loading up two separate ton bags with various rubbish…
We started the new year of 2022, after we had our mini break, by resuming the construction of Bedroom Two. We needed to finish the floor and to that goal,…
This is a long single report to cover the work during the month of December on Bedroom Two and other jobs. We wanted to get going on creating Bedroom Two…
We finished off the two air ducts we started last week. We put on the extra layer of MDF boards underneath to complete the downwards chute before it runs into…
This week, we completed the task of inserting at least one layer of PU foam board up into the rafters that we can reach from the First Floor .. the…
Today, we took an opportunity to install a new strip of LEDs up on the under side of the steel RSJ part of the Skylight. We wanted to rearrange some…
We had a week of slicing and pushing loads of PU insulation foam boards up into the rafters! We carried on with the task we started last week where we…
Among several interruptions during this week’s work, we got on with installing new framework for two sliding doors for our stand-alone Bathroom as well as for Ensuite Two. Both of…
The week was spent installing a layer of insulation inside the cavity under the hall’s flooring. We wanted to make sure that we don’t have too much leakage of valuable…
For this rather truncated week of work, we resumed the task of laying down the floorboards after a week of building the framework. One of the first things we did…