Hallway Cavities Insulated and Mains Electric Installed
The week was spent installing a layer of insulation inside the cavity under the hall’s flooring. We wanted to make sure that we don’t have too much leakage of valuable…
A DIY Selfbuild by Stephen, Shaun & Daphne
The week was spent installing a layer of insulation inside the cavity under the hall’s flooring. We wanted to make sure that we don’t have too much leakage of valuable…
For this rather truncated week of work, we resumed the task of laying down the floorboards after a week of building the framework. One of the first things we did…
This week (apart from one day on Friday lost due to other commitments) was spent constructing the complicated framework for supporting the remaining Hallways, going up to the Great room,…
We got the week going by taking our slab of OSB board we cut last week for the worktop in the Utility Room and cutting a large hole in the…
The week started with the autumn’s annual task of the Sun Shield Taken Down and Thrown Away which occupied Monday morning. Then, it was a case of continuing on with…
Today, the first thing of the new week, we went up on our roof of our temporary living quarters to take down the Sun Shield from over our long corridor…
We resumed work on our “Engine Room” within the Utility Room this week by putting on the thick heavy roof to the equipment cupboard. It is three layers of the…
After a long period of analysis, testing and weighing up the risks, we have placed an order for motorised water control valves from China, directly with the original manufacturer. It…
At the beginning of the week, we finished off preparing the Utility Room by concluding the task of putting up OSB wall boards around the door and then trimmed the…
We arrived for this new week to resume our work on preparing the Utility Room, to get it ready for installing the vast collection of equipment, tanks, switches, pipes and…