Wall Boards Are Going Up and Final Conduits Installed
After having finished the floorboards for Bedroom 3, we can walk around much easier and inspect everything. We decided to swop out the cable conduits around the windows with our…
A DIY Selfbuild by Stephen, Shaun & Daphne
After having finished the floorboards for Bedroom 3, we can walk around much easier and inspect everything. We decided to swop out the cable conduits around the windows with our…
Continuing with Bedroom 3, this week we installed more various elements into the wall and floor structure to provide additional functionality to the operation within the room like, for example,…
We continued with the work on Bedroom 3 and getting the floor, walls and windows ready. Whilst we are waiting for the deliveries, we got on with finishing the windows…
We started the new week, after completing our staircase in just four days, by fixing up the metal joist bracket to the stringers at the top of the stairs. We…
Whilst tidying up the house of the insulation foam rubbish, a new set of shelves was created to provide more room for tools and parts to be on hand for…
We needed access to the sections of the exterior walls in the utility room to get the insulation boards in, we are currently storing tools there. So today, Thursday, on…
Today saw the arrival of our new toilet and wall frame! We wanted to see and learn all the construction requirements for these wall-hanging toilets designs, like how the cistern…
For our last week of work for 2020 (and also before a long break because of Christmas and a minor medical issue), we went around the last twelve Pillars across…
This week it is the turn of the Concrete Beams and hundreds more of the concrete blocks to be hoisted up and laid out to form the roof of the…
Monday, we did two and half layers in building up our wall inside the Entertainment Room, that is over seventy blocks! We completed layer 4, then number 5 and number…