Worktop Plus Sink Installed and Started on Flooring for Hallways
We got the week going by taking our slab of OSB board we cut last week for the worktop in the Utility Room and cutting a large hole in the…
A DIY Selfbuild by Stephen, Shaun & Daphne
We got the week going by taking our slab of OSB board we cut last week for the worktop in the Utility Room and cutting a large hole in the…
The week started with the autumn’s annual task of the Sun Shield Taken Down and Thrown Away which occupied Monday morning. Then, it was a case of continuing on with…
We resumed work on our “Engine Room” within the Utility Room this week by putting on the thick heavy roof to the equipment cupboard. It is three layers of the…
At the beginning of the week, we finished off preparing the Utility Room by concluding the task of putting up OSB wall boards around the door and then trimmed the…
We arrived for this new week to resume our work on preparing the Utility Room, to get it ready for installing the vast collection of equipment, tanks, switches, pipes and…
One of the first jobs was to move the existing electricity control board from over beside the window and position it out of the way on the dividing wall between…
With the days drawing in and as each room is completed, less and less daylight is reaching the inner hallways and they are getting gloomier and gloomier plus also part…
We resumed the work on Bedroom 3 with the Wall Boards. We switched over to the tongue and groove method of joining two boards together and it seems to be…
After having finished the floorboards for Bedroom 3, we can walk around much easier and inspect everything. We decided to swop out the cable conduits around the windows with our…
Continuing with Bedroom 3, this week we installed more various elements into the wall and floor structure to provide additional functionality to the operation within the room like, for example,…