This afternoon, we dug the 2nd hole in our ground, under the house, for the next Energy Module. This one is situated under Bedroom-2 and it is 2.5 metres by 3 metres, holding about 5000 litres of water.

Module-3-Rough-dug-hole

Module-3-Rough-dug-hole

We have been putting the sand / dirt around the edges of the house where the footpaths are going, along the swimming lane and round the corner and along the garage and garden shed sections too. It is already filling up and we probably will have to hire a removal lorry with a grab to take away the excess material. We still got another two big holes and one small one to go yet!!

Peripheral-edges-raised-to-ground-level-2

Peripheral-edges-raised-to-ground-level-2

Peripheral-edges-raised-to-ground-level-1

Peripheral-edges-raised-to-ground-level-1


Tomorrow, we will level the bottom of the hole and then start cleaning the next bunch of the Aquacell crates, 30 of them this time!

Now when you watched the movie did you spot Shaun having an accident?

By Shaun