For the first three days of the this week of work, we were lucky with the weather but also unlucky as we suffered in the heat too! But we did manage to cover both sides of the “Q” Conservatory roof sections, but for only 200 slates for each side, it took us two days to get that done. Very short strips and awkward access getting up and over the gable end slowed thing down.

Q1-slated

Q1-slated


For the third day, Wednesday, we doubled checked our earlier procedure of transferring the slate positions on the first half of the “P” roof and make sure it was still lined up with our markings. Yes it was! Amazingly enough! Grin!
We then proceeded with the second half of the “P” roof section, starting as usual at the guttering line and working up the valley, putting slates across the fibre-glass trough. We reached the top of the “Q” roof and .. the moment of truth .. the meeting of the two surfaces! and the slates met together with joyous congratulations of getting it “just right”!

That was the first hurdle pass and we continued up and headed towards the top of the “O” ridge line where it meets the corner of the Skylight. After careful analysis and fiddling with different shaped slates and flashing slates too, we managed to get that lots sorted out too! Hurray and a Big Phew!!

Q2-and-start-of-P2-slated

Q2-and-start-of-P2-slated


That was pretty much the end of the work on the roof for this week as the forecast for the next three days were wet, wet and wet!
But next week, apparently, is going to be a sizzling hot hot hot weather all week, with a hot air from Europe rushing in!! Double Phew!

By Shaun