We only needed these last couple of days to finish off covering up the plastic vapour barrier membrane with our 11mm OSB boards. We completed the “J”, then the “K” and then the last two sections, “H” and “I”.

Then, we did the strip along the bottom of the “J”, “K” and “L” with a narrow 135mm wide strips of the same 11mm OSB material, this is to protect the exposed plastic membrane against accidents where something may damage it. This is our main storage area so we need to make sure that the vapour barrier is protected.

All covered in OSB 1

All covered in OSB 1

All covered in OSB 2

All covered in OSB 2

All covered in OSB 3

All covered in OSB 3

All covered in OSB 4

All covered in OSB 4



That means that we have done all the rafters that we can access from the First Floor and now we can start work on the Great Room portion of the roof rafters and get them filled up etc.
But first, we have to build a working platform right across the whole Great room, extending our Gallery so we can access the rafters without having to resort to using ladders all the time. It is very much safer and much much quicker to work on a solid level platform.

By Shaun