“H” Section All Prepared and Ready for Manufacture
These last two days has been the task of making various bits and pieces to continue manufacturing more rafters, the main task being slicing up a further 24 sheets of…
A DIY Selfbuild by Stephen, Shaun & Daphne
These last two days has been the task of making various bits and pieces to continue manufacturing more rafters, the main task being slicing up a further 24 sheets of…
This morning, in bright sunshine but chilly air, we finished installed the last two middle rafters on the “H” section of the roof. Then we spent the rest of the…
Today, in a quiet and chilly but with lovely sunshine, we got most of our rafters we had manufactured up and installed into the roof structure. The “L” section is…
After repairing the Bevel Slicing machine, we proceeded to finish off the final two “L” rafters to have their bevel ends sliced in. So we now have five “L” rafters…
After finishing the preparation work this morning, like filling up the glue dispenser bottle, cutting some more straight noggings as well as eight little “filler” noggings too, then collecting 14…
First thing this morning, we hauled out the five “J” rafters outside and got them installed up into the roof. This cleared up some much needed space in our workshop.…
This afternoon (the morning was skipped due to other commitments), we got down to the task of slicing the bevelled ends on all the remaining rafters for the “J” and…
We resumed our work (after a two day break) on manufacturing the remaining rafters for the “J” and “L” sections of the roof. There were 10 individual elements plus an…
This morning, in slightly breezy conditions, we took out the six rafters we have previously created and then completed the cutting of the bevel ends yesterday and got them all…
This morning, we finished off the last two rafters hanging over from yesterdays work. Then we adjusted our Bevel Slicing Machine to the new angle of 57 degrees which is…