Skip to content
  • Mon. Jun 9th, 2025

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed
Build Progress Ground Floor Phase 5 Roof

Sliding Door Frames Installed and Started on Insulation In Roof Rafters

Nov 6, 2021 Shaun

Among several interruptions during this week’s work, we got on with installing new framework for two sliding doors for our stand-alone Bathroom as well as for Ensuite Two. Both of…

Build Progress Ground Floor Halls Phase 5

Hallway Cavities Insulated and Mains Electric Installed

Oct 30, 2021 Shaun

The week was spent installing a layer of insulation inside the cavity under the hall’s flooring. We wanted to make sure that we don’t have too much leakage of valuable…

Build Progress Electricity Ground Floor Phase 5 Tech Cupboard

Started on Technology cupboard and Electrical panel.

Oct 23, 2021 Stephen

Stephen wanted a solo project whilst Shaun in resting, so he started on the Tech cupboard. First the two walls next to the bathroom and Storage cupboard where boarded with…

Build Progress Ground Floor Halls Phase 5

Hall floor hatches completed

Oct 19, 2021 Stephen

This week we finished cutting hatches into the hall floors on Monday and Tuesday. Then we needed a way of lifting the panels easily. So we drilled a hole 100mm…

Build Progress Ground Floor Halls Phase 5

Floorboards Laid for all Hallways

Oct 16, 2021 Shaun

For this rather truncated week of work, we resumed the task of laying down the floorboards after a week of building the framework. One of the first things we did…

Build Progress Ground Floor Halls Phase 5

Finished Framework for Hallway Flooring

Oct 9, 2021 Shaun

This week (apart from one day on Friday lost due to other commitments) was spent constructing the complicated framework for supporting the remaining Hallways, going up to the Great room,…

Build Progress Ground Floor Halls Phase 5 Utility Room

Worktop Plus Sink Installed and Started on Flooring for Hallways

Oct 2, 2021 Shaun

We got the week going by taking our slab of OSB board we cut last week for the worktop in the Utility Room and cutting a large hole in the…

Automation Build Progress Orders and Procurement Phase 5

Another order from China

Sep 26, 2021 Stephen

After buying the valves last week, we started looking for some of the other things needed for automating the house. The next things are Flow sensors – to measure how…

Build Progress Ground Floor Phase 5 Utility Room

Completed First Stage of Plumbing Plus Also Flooring

Sep 26, 2021 Shaun

The week started with the autumn’s annual task of the Sun Shield Taken Down and Thrown Away which occupied Monday morning. Then, it was a case of continuing on with…

Site Maintenance Temporary Accommodations

Sun Shield Taken Down and Thrown Away

Sep 20, 2021 Shaun

Today, the first thing of the new week, we went up on our roof of our temporary living quarters to take down the Sun Shield from over our long corridor…

Posts pagination

1 … 12 13 14 … 148

Roselea

A DIY Selfbuild by Stephen, Shaun & Daphne

Proudly powered by WordPress | Theme: Newsup by Themeansar.

  • Home
  • About
  • Contact Us
  • Design
    • Electricity
    • Energy
      • Solar Electricity
      • Solar Thermal
    • First Floor
    • Garage
    • Ground Floor
    • Ground Works
    • Roof
    • Site
    • Ventilation
    • Walls
    • Water
      • Rain Water
      • Sewage
  • Find Us
  • Pictures
    • Material Samples
    • Temporary Building
  • Plans
    • Structural Engineer Apr 2013
    • Groundworks September 2010
    • Building control May 2010
    • Planning April 10
    • Planning October 09
    • Planning August 2009
  • Tasks
  • Webcam Feed