“J” Roof Section Fully Complete and Preparation Begins for “H” and “P” Sections
First thing this morning, we hauled out the five “J” rafters outside and got them installed up into the roof. This cleared up some much needed space in our workshop.…
A DIY Selfbuild by Stephen, Shaun & Daphne
First thing this morning, we hauled out the five “J” rafters outside and got them installed up into the roof. This cleared up some much needed space in our workshop.…
This afternoon (the morning was skipped due to other commitments), we got down to the task of slicing the bevelled ends on all the remaining rafters for the “J” and…
We resumed our work (after a two day break) on manufacturing the remaining rafters for the “J” and “L” sections of the roof. There were 10 individual elements plus an…
This morning, in slightly breezy conditions, we took out the six rafters we have previously created and then completed the cutting of the bevel ends yesterday and got them all…
This morning, we finished off the last two rafters hanging over from yesterdays work. Then we adjusted our Bevel Slicing Machine to the new angle of 57 degrees which is…
For the start of a new week, we start on a new section of the roof. This time, it is the “J” and “L” sections, which are over Bedroom Two…
Today, we finally got the eleven rafters up and installed in the Front Extension portion of the building, completing six rafters on the “B” section of the roof and a…
On a very, very chilly day (temperature floating around the low single digits!), we were in the workshop slicing the bevelled ends on our eleven rafters we made yesterday. The…
After a delayed start, we got on with the creation of the rafters to complete the “B” and “D” roof sections. But first, we filled up our “compressed air” glue …
First thing this morning, we took outside the four and a half rafters created yesterday and got them installed up into the roof framework over the front door and Entertainment…