Today, in a quiet and chilly but with lovely sunshine, we got most of our rafters we had manufactured up and installed into the roof  structure.
The “L” section is now complete, all five rafters were done before lunch.

Roof-L-Finished

Roof-L-Finished


Then the “P” section was finished as the daylight faded away at 4pm (no picture, too dark!)
And finally, two of the four rafters for the “H” section was installed in total darkness, apart from our powerful floodlight shining down on the scene!
Rafters-H10-and-H11

Rafters-H10-and-H11


On Monday, we will finish off the middle portion of the “H” section and then we can measure up the necessary distances to start manufacturing the filling in set of rafters for both the “P” and “H” triangular portions, either side of the middle bit we have done today.

By Shaun

Leave a Reply