With a lovely prospect of good weather ahead of us, we got on putting up the final rows, about 13 of them, of the tile battens to finish off preparing them for the slates. But before the slates could go on, there were plenty of other tasks to be performed. The next job was to nail up the flashing battens along the two hips and two ridges, using a string to guide us and keep us on the straight and narrow.
The other job we did was to put up the Skylight kerb flashing strip made of the aluminium metal sheets, with the rubber membrane to actually provide the diversion of the rain water.
After that, the metal mesh went on the gutters, fixed down as usual with the thin oak strips to clamp down the edge of the mesh and rubber membrane on the gutter.
Skipping over a 4 hour job in helping a friend out with a plumbing crisis, we continued in preparing the roof sections, this time in doing the special bull-nose upright flashing strips on the two hips and again the two ridges too. This was made up of the shaped wooden strips with the woven glass-fibre ribbon wrapped over the top of the bull nose, all sitting on the rubber membrane that will provide the protection against the rain water. We put on three coats of resin, the last layer being a grey flexible top-coat to finish it off nicely.

Whole of P and Q Roof Sections All Prepared, Flashing Layers Assembled and Ready to Slate!

O-P1-roofs-ready-to-slate

Whole of P and Q Roof Sections All Prepared, Flashing Layers Assembled and Ready to Slate!

Q-roof-ready-to-slate



This concludes the preparation work for these sections of the roof (the “N”, “O”, “P” and “Q”) and we can start slating .. .. but the last day of the week, the Saturday, was lost to rain but we worked inside in the workshop instead.

By Shaun

Leave a Reply