Started Installing Joists for First Floor
We have started the process of installing the joists for the First Floor. The last two and half days were spent on several tasks, like for example, marking out on…
A DIY Selfbuild by Stephen, Shaun & Daphne
We have started the process of installing the joists for the First Floor. The last two and half days were spent on several tasks, like for example, marking out on…
This morning and yesterday were spent on repairing the broken wall and repainting the street sign for our Loke after the delivery lorry with our I-Beams had misjudged things and…
In the morning we prepared an area to store the beams next to the house. The lorry arrived at 1:25pm with the 66 special I-Beams on a open flatbed vehicle,…
Monday is the big day with the arrival of 66 special timber I-Beams, the last three days have been spent preparing for this happy day. So, we adapted our large…
The other piece of equipment we made while we waited for this day, was to build a special chop saw table to cope with slicing these I-Beams. Their physical size,…
At the beginning of the three weeks waiting for the arrival of our First Floor Joists, we sat down to analyse all requirements of providing connections to the outside world…
Our Glass Wool insulation we ordered last week has arrived today. The delivery truck parked in our local Tesco Express (after asking the staff inside the shop for permissions) and…
We continued the task of putting up reinforced wall posts for the hanging toilets for the cloakroom and for the en-suite of Bedroom 3 where we had to put down…