We had a very disrupted week of work, losing three and a half days, due to other commitments and meetings. It is just one of those things that happens now and again.
We at least, got all the breathable membrane up on Monday and Tuesday so the “P” and “Q” sections of the roof are both now protected against rainwater, held down with a few vertical battens and some horizontal tile battens.

P and Q All Covered in Membrane and Almost Complete with Tile Battens

Membrane-on-P1-Q1

P and Q All Covered in Membrane and Almost Complete with Tile Battens

Membrane-on-Q2-P2



The final day, Saturday, we did a solid day of work of putting up all the rest of the counter battens, and got most of the tile battens nailed up too. We had to make a slight adjustment to some of the horizontal battens near the ridge line of the Q (the Conservatory) roof where the two “P” half sections meets together, there was a little 20mm mismatch to the lines of the battens so we “corrected” four lines of battens just below on the right hand side so there wasn’t a sudden “jump” in the line of the Slates.
P and Q All Covered in Membrane and Almost Complete with Tile Battens

Most-Tile-battens-on-P1

P and Q All Covered in Membrane and Almost Complete with Tile Battens

Most-tile-battens-on-P2-Q2



Next week, we hope that we will get in a full week of work and make solid progress on finishing the “N”, “O” and some of the “P” and “Q” roof sections, putting on thousands of Slates etc.!