The last two days of the week (Friday and Saturday) were nice days so we got on with installing the two Downpipe Channel modules for the P-Q valley that forms part of the extension part of the building for the Conservatory coming in the future.
Then we got all the guttering done, for all the P (first section and second section either side of the Q conservatory) and the first third of the A section along the front of the house.
Finally, we got the layers of the plywood strips installed for the p-A Hip corner of the roof so we could fibre glass all the complicated junctions and corners.
So on Monday (weather permitting) we can fibre-glass these junctions and have them all sealed, ready for the rubber membrane to go on along the two P small sections.